5.3 Simulation of earthworks and retaining system for a large excavation
(Geiser et al., 2002)
5.3.1 Model
In the
neighbourhood of Geneva, the construction of a watch production centre
has been planned. The project involves the execution of a large excavation
in soft and saturated clays. It concerns a 145 x
Figure 30: Excavation during the earthworks.
A 3D numerical simulation has been conducted in order to control and optimise all the components interacting in the project. A similar case (large dimensions, similar soil conditions and retaining system) constructed in the 1970’s has been used as a real-scale test in order to precise the soil parameters and the hydro-mechanical behaviour with the help of a back analysis (Fig. 31).
Figure 31: Methodology comparison.
In the actual project, the soils consist mainly of soft and compressible silty clay and silty clay loam, over a thick compact Wurmian moraine. Based on the geotechnical study, six principal layers were schematically defined. It was immediately observed, that an "advanced" constitutive law (here Cap model) was essential to describe correctly the fined-grained soils. The parametric study emphasized also the influence of the compressibility parameter l on the observed displacements.
The
change in the pore-water pressure was observed to be the main factor
influencing the general behaviour in this project. As the soil permeabilities
are low, the hydraulic conditions remain transient during the construction.
For a year long excavation, the pore-water pressure looses about 25 to 30
% of its initial value. After reproducing these time-effects on a 2D model,
a "pseudo-transient" model was developed for the 3D approach, in order
to avoid days-long calculations with a time dependent problem.
The soil is modelled with about 10’000 8-nodes brick
elements. The EAS (enhanced assumed strains) finite element technology is
selected in order to prevent these elements to lock volumetrically. Structural
elements (see Figure 32) can be divided into three sub-categories: slurry
walls and mat foundations are modelled with thin shells (Mindlin-Reissner
hypothesis), while 2-nodes trusses are used to introduce supporting piles
and bracing. Finally, the circular reinforced concrete beam and the
external slurry wall stiffener are introduced as Timoshenko beam elements.
An initial state analysis is conducted first in
order to start with a non-zero stress field in equilibrium associated
with a zero displacement field. After that, twelve construction and excavation
steps take place as follows: first, the superficial soil layer is removed
(
Figure 32: Structural elements static system.
Figure 33: Excavation stages.
The external slurry wall is reinforced by counterforts in the execution
project. Introducing each counterfort into the global 3D mesh would
have been too tedious. An auxiliary analysis has therefore been conducted
on a smaller part of the wall in order to estimate the influence of the
absence of the counterforts. Results show that settlements are overestimated
by 20 to 30 % when modelling the wall with thin shells; the general behaviour
of the retaining system is however correctly reproduced.
5.3.2 Results
The vertical
displacements after the first excavation step are depicted in Figure
34. The maximal settlement at this time is located near the excavation
and reaches
Figure 34: Vertical displacements after the first excavation step
Figure 35: Settlements at the end of the earthworks
A cut parallel
to the northern wall crossing the excavation at the middle of the side walls
shows the predicted deformation of the system at the end of the earthworks
(Figure 36). There is a
Figure 36: Horizontal colour maps and deformed mesh
Figure
37 shows the predicted repartition of the pore-water pressures behind
the external slurry wall with looses of about 25 to 30 % of the initial
hydrostatic pressures. As in situ measurements are now available, they
are also represented, highlighting a good correlation with the predicted
values.
Figure 37: Pore-water pressure behind the external slurry wall.
An integrated
parametric analysis, backed with the experience of the constructors,
helps the project engineers optimize the costs of the structure supporting
the opening, in the sense that it gives them a qualitative analysis on
the effective participation of any structural element to the excavation
stability. It can be noticed
in particular that the influence of the two supporting slurry walls linking
the external and the circular walls on forces and displacements is little,
as shown in Figure 38.
Figure 38: Comparison of the slurry walls deformation
at the end of the excavation, with or without the supporting walls. Horizontal
cut at the galleries’ bottom level.
Another
parametric study on the circular buried slurry wall has been conducted
in order to check the influence of the concrete quality (see Figure 39).
This excavation is currently under construction,
and the first set of in situ measures (inclinometers, pore-pressure cells,
optical fibers) have just been analyzed. Of course, modifications have
occurred; in particular the excavation steps have been changed. A new
calculation incorporating better the reality would be necessary, to allow
a rigorous comparison. However, in Figure 40, the predicted deformations
of the external slurry wall are compared with the actual observations. A
rather good agreement can be found between the two curves, in particular
in the order of magnitude of the displacements.
Figure 39: Horizontal membrane force in the circular wall.
Comparison between E = 2e7 (up) and E = 1e7 kN/m2 (down).
Figure 40: Horizontal displacement
of the wall, prediction vs. field measure at two depths:
The main
discrepancies between prediction and measure can be explained in the
following way:
- on the one hand at y =
- on the
other hand, at y =
The pore water pressures have also been measured on the field and the “pseudo-transient” computation has shown to be efficient (see Figure 37).
To conclude, this example shows the importance of having complete
initial data at hand for a 3D numerical simulation. The use of a real-scale
test is also shown to be very useful in order to calibrate the parameters
influencing most of the simulations, in particular the pore-water pressure
decrease and the soil compressibilities leading to the necessity to choose
an adapted constitutive law (Cap model). The time-consuming aspect of
3D numerical simulations can be reduced in conducting different parallel
studies (influence of the counterforts, pseudo-transient calculation, no
interface elements).
The comparison with in situ measures has validated the a priori predictions.